Current Visitor

This is default featured slide 1 title

Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.

This is default featured slide 2 title

Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.

This is default featured slide 3 title

Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.

This is default featured slide 4 title

Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.

This is default featured slide 5 title

Go to Blogger edit html and find these sentences.Now replace these sentences with your own descriptions.

Sabtu, 12 Disember 2015

PERADUAN TEKA DAN MENANG

Peraduan Teka Dan Menang Bilangan Mukasurat Untuk 5 buah buku di dalam gambar di atas


JOM SERTAI

1. PERADUAN TEKA DAN MENANG UNTUK BILANGAN MUKA SURAT BUKU DALAM GAMBAR DI ATAS

2. HADIAH PERTANDINGAN : RM 50.00 TUNAI

3. SYARAT PERTANDINGAN

a) Sila Like Page FB Jualbukuteknikal http://on.fb.me/1O0853m

b) Daftar email anda pada kotak email di bawah sebelah kiri
c) Hantar jawapan bilangan mukasurat anda pada alamat bukuteknikal@gmail.com 
beserta nama dan nombor telefon

4. TEMPOH PERTANDINGAN ADALAH SELAMA  1 BULAN IAITU SEHINGGA 12 JANUARI 2016.

5, PEMENANG AKAN DIPILIH BERDASARKAN KETEPATAN ATAU TERHAMPIR KEPADA JAWAPAN YANG BETUL

6, PEMENANG AKAN DIHUBUNGI MELALUI EMAIL 

7, KEPUTUSAN PENGADIL ADALAH MUKTAMAD

8. SEBARANG PERTANYAAN. BOLEH DI EMAIL KEPADA bukuteknikal@gmail.com

Name
Email
Email Marketing by TrafficWave.net




         


INFO BUKU BERTERUSAN

Sekiranya anda berminat untuk mendapatkan info-info buku teknikal secara berterusan di dalam email anda. Sila daftarkan email anda di dalam web www.azilanmazahar.com atau pada kotak email di bawah








Name
Email
Email Marketing by TrafficWave.net

Selasa, 8 Disember 2015

SOFT COPY SMM2


SEMESTER BAHARU DI IPTA TELAH BERMULA. KEPADA PARA PELAJAR, INGIN MENDAPATKAN VERSI SOFT COPY BOLEH WASSAP KEPADA ADMIN 012 387 5655 ATAU TINGGALKAN EMAIL PADA LINK BERIKUT BAGI MENDAPAT INFO TAMBAHAN BAGI MENGETAHU CARA PENGIRAAN KOS KONKRIT DENGAN LEBIH MUDAH www.azilanmazahar.com 

RAHSIA UNTUK MENDAPATKAN JADUAL PENGIRAAN KONKRIT SECARA PERCUMA

Penyediaan anggaran harga untuk konkrit akan menjadi lebih mudah dengan hanya memasukkan kuantiti konkrit di dalam jadual yang disediakan. Gred konkrit yang boleh digunakan adalah dari Grade 10 sehingga Grade 50.
Hanya dengan memasukkan data kuantiti konkrit ke dalam jadual tersebut, pengiraan bahan-bahan yang terkandung di dalam konkrit seperti simen, pasir dan aggragate akan dikira secara automatik.
Penggunaan jadual ini sangat berguna kepada mereka yang berada di dalam sektor pembinaan seperti kontraktor, perunding, pemaju, pelajar IPTA dan orang awam.
Jadual ini telah dibangunkan khas melalui perisian ‘microsoft excel’ dengan merujuk kepada contoh berikut:




Sabtu, 5 Disember 2015

Berita : Kad Hijau CIDB


Berdasarkan kepada keratan akhbar di atas menunjukkan . Pekerja binaan wajib ada kad hijau mulai Jun 2016. Sekiranya gagal, ia boleh dikenakan denda RM 5,000 iaitu denda maksimum. Kepada yang tiada, ayuh pergi ke pejabat CIDB terhampir untuk dapatkan maklumat .


Pejabat-pejabat Lembaga Pembangunan Industri Pembinaan Malaysia (CIDB)
CIDB WILAYAH PERSEKUTUAN KUALA LUMPUR
Tingkat 9, Menara Dato' Onn,
Pusat Dagangan Dunia Putra,
No 45, Jalan Tun Ismail,
50480 Kuala Lumpur.
Tel : 03-4045 3800 / 3851
Faks : 03-4047 3858
PUSAT PERKHIDMATAN
CIDB WILAYAH PERSEKUTUAN KUALA LUMPUR
(Pendaftaran Kontraktor, Kad Hijau & Levi)
Tingkat bawah Blok E,
Lot 8, Jalan Chan Sow Lin,
55200 Kuala Lumpur.
Tel : 03-9281 6070
Faks : 03-9281 6077
CIDB NEGERI PERAK
Lot 5.02, Tingkat 5,
Bangunan KWSP,
Jalan Greentown,
30450 Ipoh, Perak.
Tel: 05 – 242 3488
Faks : 05 – 255 5488
CIDB NEGERI MELAKA
No. 31-1, Jalan TU 49A
Kompleks Komersial Boulevard
Taman Tasik Utama,
75450 Ayer Keroh, Melaka
Tel :  06-232 8895
Faks:  06-232 8950

CIDB NEGERI JOHOR
Lot 2067, Batu 3,
Jalan Tampoi,
81200 Johor Bahru,
Johor.
Tel : 07-234 4808
Faks : 07-234 4807

CIDB NEGERI TERENGGANU
Tingkat 7,
Menara Yayasan Islam Terengganu
Jalan Sultan Omar,
20300 Kuala Terengganu, Terengganu.
Tel : 09-624 5311
Faks : 09-623 8973


CIDB NEGERI KELANTAN
No. U7.2, Tingkat 7,
Menara Perbadanan,
Jalan Tengku Petra Semerak,
15000 Kota Bharu, Kelantan.
Tel: 09 – 744 4311


CIDB NEGERI PAHANG
A1, Tingkat Bawah
jalan Seri Kuantan 2
Seri Kuantan Square
25050 Kuantan, Pahang.
Tel: 09 – 517 8734 

CIDB NEGERI SABAH
Blok A, Tingkat 4,
Bangunan KWSP,
88100 Kota Kinabalu,
Sabah.
Tel: 088 – 244 423/658/506
Faks : 088 – 242 481

CIDB NEGERI SABAH (CAWANGAN TAWAU)
Tingkat 1 Wisma Gek Poh,
Batu 1, Jalan Dunlop / Kuhara
Beg Berkunci No. 7,
91009 Tawau, Sabah.
Tel: 089 – 777 841/842
Faks : 089 – 777 840


CIDB NEGERI SARAWAK
Tingkat 1, Blok A, Kompleks CIDB,
Jalan Sultan Tengah,
93050 Kuching, Sarawak.
Tel: 082 – 445 833
Faks : 082 – 447 833

CIDB NEGERI SARAWAK (CAWANGAN MIRI)
Lot 1140, Block 9,
Miri Concession Land District,
Miri Waterfront,
98000 Miri Sarawak.
Tel: 085 – 417 431
Faks : 085 – 417 432

CIDB NEGERI KEDAH
Lot 7&8,
Kompleks Perniagaan Asas Jaya,
Jalan Stadium,
05100 Alor Setar, Kedah.
Tel: 04-733 1243
Faks : 04-733 1175

CIDB NEGERI SELANGOR
Tingkat 5, Wisma PKPS
Persiaran Perbandaran,Seksyen 14
40675 Shah Alam
SELANGOR
Tel: 03 - 5512 8600
Faks : 03 - 5512 8620

CIDB NEGERI PERLIS
No 10 Jalan Tuanku Syed Putra (Jalan Kangar-Alor Setar),
Seriab, 01000 Perlis Indera Kayangan.
Tel : 04-9781 243
Faks : 04-9781 244
 
CIDB PULAU PINANG
Lot 9.01, Tingkat 9, Bangunan KWSP,
No. 3009 Off Lebuh Tenggiri 2,
Bandar Seberang Jaya,
13700 Seberang Jaya, Pulau Pinang.
Tel: 04 – 390 2448
Faks: 04 – 390 7448

CIDB NEGERI SEMBILAN
Wisma KoCIDB
Lot D30, Persiaran Utama S2/B2
Seremban 2
70300 Seremban
Negeri Sembilan
Tel : 06 - 601 6311
Faks : 06 - 601 7311


Jumaat, 20 November 2015

PENGELUARAN SIJIL SIAP KERJA (CPC) MENGIKUT BORANG JKR D&B (REKA DAN BINA) VERSI 2002, 2007 DAN 2010

Add caption

BORANG KONTRAK JKR D&B VERSI 2010 DAN VERSI 2007

Add caption
BORANG KONTRAK JKR D&B VERSI 2002


Merujuk kepada ketiga-tiga jenis COC Design And Build di atas menunjukkan untuk kontrak menggunakan versi 2007 dan 2010 memerlukan pihak kontraktor mendapatkan CCC terlebih dahulu sebelum CPC dikeluarkan. Manakala untuk Borang Kontrak versi 2002 tidak menyatakan keperluan untuk mendapat CCC terlebih dahulu sebelum CPC dikeluarkan.

JKR DB 2002: Klausa 41
JKR DB 2007 : Klausa 44.2
JKR DB 2010: Klausa 44.1

Off Topic : Bengkel Bongkar Rahsia Facebook Dan Instagram

BENGKEL BONGKAR RAHSIA FACEBOOK DAN INSTAGRAM



CEPAT! TEMPAT TERHAD!



GEMPAR~RAHSIA AKAN DIBUKA

Di program����

BENGKEL BONGKAR RAHSIA BUAT DUIT DARI FB &IG

Tarikh : 29/11/15 (ahad)

Masa: 9 -5pm

Tempat: 
Dewan Kuliah Pusat 1,Kampus Sultan Azlan Shah, Proton City, 
Universiti Pendidikan Sultan Idris, Tg.Malim Perak.

Yuran: RM450 di turunkan kepada HANYA RM80 termasuk makan!!

Anjuran unit Pusat Pembangunan Keushawanan (PPK) UPSI & COACH AZHAR

Antara pengisian...

1. Punca Banyak Iklan Di Fb Tidak Berkesan
2. Apa Itu Autopost
3. Adakah Fanpages Berkesan
4. Teknik Add 300 friend sehari ke FB
5. Teknik Add Prospek Yg Tepat
6. Teknik IG
7. Naikkan Follower IG
8. Baik Buruk Open Dan Privite IG
9. Baik Buruk Sikit/Banyak Follower IG
10. Kuasa Hastag
11. Jadual Hastag
12. Cara Menyimpan Data Prospek Dan Pelanggan Yg Betul
13. Rahsia Internet Marketer
Teknik Kebun
Teknik Sniper
Teknik Kolam
Teknik Semut
Teknik Gerila


����������
Semua Peserta Bakal Menerima:
1. Percuma 25 Video Panduan Membina Web Promosi Bernilai Rm200
2. Senarai Hastag Niaga Sebanyak 3000
3. Senarai  100 IG Kuat Malaysia

Tunggu✋✋✋ada lagi....PERCUMA 2 domain berharga RM120 setiap satu, tajaan dari Mynic Malaysia


(Pihak PPK Berbesar Hati Bekerjasama Dengan Coach Azhar Hanya Melibatkan Yuran Rm80 Berbanding Yuran Sebenar Berharga Rm450)

Anda pasti rugi jika tidak hadirkan diri

Daftar awal dan buat bayaran segera kepada akaun maybank 5144 7705 4177 (Azilan).

CEPAT!! TEMPAT TERHAD!
CEPAT!! TEMPAT TERHAD!
CEPAT!! TEMPAT TERHAD!

Hubungi 012 3875655 (AZILAN) untuk tempahan tempat dan pendaftaran.

Berikan maklumat
1. Nama
2. No telefon
3. Email
4. Alamat surat menyurat
5. Bukti bayaran

JOM LAYARI




Sabtu, 14 November 2015

Kontrak Reka dan Bina menurut pemahaman saya,hee, hee

Kontrak Reka dan Bina atau Design And Build bermaksud, sesuatu projek dilaksanakan dengan Kontraktor menyediakan rekabentuk dan melaksanakan kerja pembinaan berdasarkan kehendak projek atau need of statement dari pihak klien.

Pihak yang merekabentuk bagi pihak kontraktor ialah perunding-perunding yang terdiri daripada Arkitek, Jurutera Awam, Mekanikal, Elektrik dan Juruukur Bahan. Kesemua perunding diletakkan di bawah tanggungjawab pihak kontraktor.

Pegawai Penguasa yang mentadbir pihak klien untuk kontrak ini dikenali sebagai Pengarah Projek (PP) atau Project Director (PD).

Borang kontrak kontrak reka dan bina bagi projek kerajaan ialah menggunakan Borang Kontrak JKR DB (1/2010. Borang ini mengandungi 79 Klausa syarat-syarat Kontrak.

Dalam syarat-syarat kontrak ini mengandungi perkara-perkara seperti berikut:


  1. Kerja hendaklah dilaksanakan dalam tempoh 2 minggu dari tarikh milik tapak.
  2. Program kerja atau work programme perlu disediakan dalam tempoh 2 minggu dari milik tapak dan pihak PD perlu mengesahkan dalam tempoh 21 hari (Klausa 13.5)
  3. Pihak kontraktor perlu menyediakan bon pelaksanaan dalam nilai 5% dari nilai kontrak
  4. Pihak kontraktor perlu mengemukakan design gerenti sebelum CPC keluar dengan nilai 5% dan berkuatkuasa selama 5 tahun dari tarikh siap (Klausa 14.3)
  5. Maksud VO ialah penambahan, pengurangan atau penggantian (Klausa 23.0)
(tak abis lagi) nanti sambung.

Selasa, 3 November 2015

‘Time at large’ dalam Kontrak

          ‘Time at large’ dalam Kontrak
          Ini adalah keadaan di mana tarikh siap telah pun berlalu tetapi kerja di tapakbina masih lagi belum siap dan TIADA sebarang Perakuan Kerja Tak Siap ataupun Perakuan Lanjutan Masa yang telah dikeluarkan oleh PP.
         Kesannya adalah masa tidak lagi menjadi ‘ essence’ kepada kontrak dan kontraktor mempunyai hak untuk menyiapkan projek pada tempoh yang difikirkannya sesuai.

          PP hendaklah mengelakkan situasi sebegini kerana keadan ini akan menjejaskan kepentingan majikan untuk mengambil tindakan undang undang ke atas kontraktor.

Jumaat, 2 Oktober 2015

Buku Pengurusan Perolehan Sebutharga Dan Tender Konvensional

Tajuk: Pengurusan Perolehan Sebutharga dan Tender Konvensional
Penerbit: Penerbit UTHM
Penulis : Norazilan Bin Mazahar
Harga: RM 39.00

Sinopsis

Buku Pengurusan Perolehan Sebutharga dan Tender Konvensional telah berjaya dihasilkan dan berada di tangan pembaca. Buku ini sesuai untuk menjadi rujukan asas kepada pelajar-pelajar Universiti Awam(UA), Institut Pengajian Tinggi (IPT), kontraktor, perunding, pemaju atau orang awam yang berminat untuk mengetahui dan mendalami kefahaman berkenaan tatacara  perolehan tender konvensional dan sebutharga di agensi kerajaan.

Buku ini juga sesuai dan berguna untuk rujukan kepada graduan dalam bidang Ukur Bahan, Arkitek atau Kejuruteraan yang bakal menamatkan pengajian sebelum melangkah ke alam pekerjaan dan akan terlibat secara langsung atau tidak langsung dengan tatacara perolehan di agensi kerajaan.



Isnin, 28 September 2015

Perbezaan Antara Tender Secara Jabatan dan Tender Menggunakan Khidmat perunding

Bil
Tender Secara Jabatan
(Tender In House)
Tender Menggunakan Khidmat
Perunding
1.
Pelaksanaan projek diuruskan sendiri oleh pihak Jabatan
Pelaksanaan projek diuruskan dengan menggunakan khidmat perunding
2.
Melibatkan kos projek yang berskala kecil
Melibatkan kos projek yang berskala besar
3.
Melibatkan skop kerja yang mudah tanpa melibatkan kehendak rekabentuk atau lukisan yang kompleks
Melibatkan skop kerja dan rekabentuk atau lukisan yang kompleks
4
Tempoh masa untuk proses perolehan dapat disingkatkan
Tempoh masa menjadi panjang kerana melibatkan proses pelantikan perunding
5
Penjimatan kos dalam perkhidmatan penyediaan rekabentuk kerana  disediakan sendiri oleh pihak jabatan
Kos pelantikan perunding dikira dan termasuk sebagai kos siling projek

Sabtu, 29 Ogos 2015

Perbezaan warna safety helmet di tapak bina

Jumaat, 28 Ogos 2015

Ahli Profesional Projek Pembinaan

Ahad, 23 Ogos 2015

Buku Asas Pengurusan Pembinaan

Jumaat, 21 Ogos 2015

Sijil Bayaran JKR 66 terkini

Untuk makluman semua

Buku Ahli Profesional Projek Pembinaan


Khamis, 20 Ogos 2015

Scafolding


Scafolding atau Peranca sering digunakan untuk pembinaan di kawasan bangunan tinggi. Ia mempunyai pelbagai fungsi untuk menyokong kerja-kerja pembinaan seperti berikut:
a) Mengecat dinding bangunan,
b) Memasang ikatan batu bata,
c) Melepa simen plaster pada dinding bangunan
d) Kerja-kerja pendawaian pada aras yang tinggi
e) Memasang siling pada aras bumbung

Ia mempunyai komponen-komponen seperti cat walk, main frame, horizontol, cross brace, join dan svivel castor.

Pemasangan peranca ini perlu dilakukan oleh orang yang kompeten bagi mengelakkan permasalahan berlaku ketika kerja berjalan.

Perakuan Sijil Separa

Sijil Perakuan Siap Separa

Apabila sesuatu projek yang sedang dilaksanakan itu telah siap secara separa atau telah mencapai keperluan untuk bangunan tersebut berfungsi serta pihak Pegawai Penguasa (SO) telah berpuas hati. Pihak Pegawai Penguasa (SO) tersebut boleh memperakukan kepada pihak kontraktor untuk pengeluaran Sijil Perakuan Siap Separa .

Peruntukan klausa di dalam borang kontrak atau Conditions Of Contract yang berkaitan dengan Perakuan Sijil Perakuan Siap Kerja (CPC) adalah seperti berikut:

a) Klausa 42.0- Borang JKR 203A versi 2010
b) Klausa 46.1- Borang Kontrak Design And Build (PWD Form DB/T) version 2010

Kesan daripada pengeluaran Sijil Perakuan Siap Kerja (CPC) adalah seperti berikut:

1- Tempoh Liabiliti Kecacatan (DLP) bermula iaitu selama 1 tahun untuk kontrak konvensional dan selama 2 tahun untuk kontrak secara design and build akan berlaku kepada  bangunan yang diterima secara separa

2-Pengiraan LAD perlu dikira semula dengan membuat pengiraan terhadap bangunan yang belum siap sepenuhnya.

3. Pelepasan Bon Pelaksanaan sepenuhnya oleh pihak klien kepada kontraktor hanya boleh dilakukan setelah Sijil Siap Memperbaiki Kecacatan (CMGD) dikeluarkan kepada seluruh bangunan.